Power - Canado https://canadoconstruction-ca.com Construction Fri, 07 Oct 2022 10:31:12 +0000 en-US hourly 1 https://wordpress.org/?v=6.0.3 https://canadoconstruction-ca.com/wp-content/uploads/2022/10/Untitled-design-1-73x73.png Power - Canado https://canadoconstruction-ca.com 32 32 Falls Hydroelectric https://canadoconstruction-ca.com/portfolio/falls-hydroelectric/ Sun, 15 Aug 2021 14:02:23 +0000 http://layerdrops.com/kontinwp/portfolio/bridge-construction-copy-copy-copy-copy-copy/ H.J. O’Connell (HJOC), a subsidiary of Canado, was the lead in the joint venture, IKC-ONE Earthwork Constructors consortium, which included the participation of the Labrador Innu. The contract included overburden and rock excavation of the intake, powerhouse, spillway, separation wall, switchyard and converter stations and dams at the site of the 824 megawatt hydroelectric generating […]

The post Falls Hydroelectric first appeared on Canado.

]]>
H.J. O’Connell (HJOC), a subsidiary of Canado, was the lead in the joint venture, IKC-ONE Earthwork Constructors consortium, which included the participation of the Labrador Innu. The contract included overburden and rock excavation of the intake, powerhouse, spillway, separation wall, switchyard and converter stations and dams at the site of the 824 megawatt hydroelectric generating station in central Labrador.

The team worked around-the-clock to complete the project before the winter months with a crew of 400 and 200 pieces of heavy equipment. Almost 300,000 linear metres of rock was drilled with 75- to 165-millimetre holes for blasting. The rock removal commenced at 20 metres above the river level and concluded at 32 metres below water level. In addition, 150,000 cubic metres of earthfill cofferdams and 37,000 cubic metres of roller compacted concrete cofferdams were built.

At the completion of the project, over 2.7 million cubic metres of earth was moved, over 1.8 million cubic metres of rock blasting and removal was completed, and 15,000 cubic metres of underwater rock was removed. With the success of this project, HJO looks forwardto additional contract awards for this ongoing challenging project.

 

 

The post Falls Hydroelectric first appeared on Canado.

]]>
Wuskwatim Generating Station https://canadoconstruction-ca.com/portfolio/wuskwatim-generating-station/ Sun, 15 Aug 2021 14:02:16 +0000 http://layerdrops.com/kontinwp/portfolio/bridge-construction-copy-copy-copy/ The Wuskwatim Generating Station project was comprised of the concrete supply and placement for the spillway, service bay, intake and powerhouse structures, as well as construction of the main dam and all remaining excavation required for the principal structures. As a member of the project consortium, H.J. O’Connell, a division of Bird, provided world class […]

The post Wuskwatim Generating Station first appeared on Canado.

]]>
The Wuskwatim Generating Station project was comprised of the concrete supply and placement for the spillway, service bay, intake and powerhouse structures, as well as construction of the main dam and all remaining excavation required for the principal structures. As a member of the project consortium, H.J. O’Connell, a division of Bird, provided world class construction services to the Wuskwatim Generating Station in concert with the utmost respect for the environment and the achievement of meaningful training and long-term benefits to the people of the area.

  • CLIENT : Manitoba Hydro
  • CONSULTANT : KGS Acres Ltd.
  • CONTRACT TYPE : Unit Price
  • PROJECT VALUE
    $400,000,000
  • PROJECT SIZE : 106,273 cu. m of concrete 64,382 sq. m of formwork  7,500 tons of steel
  • Duration  : 46 months

The post Wuskwatim Generating Station first appeared on Canado.

]]>